From Diane Ahern, UCCA’s corresponding secretary:
Repaving work began Friday, April 4, on Gullstrand between Governor and Florey, including Tula Ct. At times, the project is likely to impact Gardens Park and the Governor/ Gullstrand intersection.
Preliminary work for a repaving project for Tula Ct and Gullstrand will begin on Friday, April 4.
Work will begin with curbs and sidewalks and them move on to repaving. The project will likely impact the Governor and Gullstrand intersection.
Project outreach materials were distributed to all residents on Tula Ct and on Gullstrand with information about this project. Thank you to the Gullstrand and Tula Court residents who provided screen prints of information they received from the City engineering department.Please see the attached images.
Please note: At present, the repaving of Gullstrand Street is scheduled for June 12th. However, please note that this date may be subject to change depending on project progress with the curbs and sidewalks project and other factors.
This project will affect all of us who use Governor and Gullstrand to travel to and from our neighborhood.
- For more information, navigate to Tula Ct using the map on the CIP Project Information page for CIP project B24012 at : https://www.sandiego.gov/cip/project-info
- For more information, send an email with subject line “Asphalt Overlay Group 2402 – for Gullstrand and Tula Ct in University City” and email your request to City Engineering at: ENGINEERING@sandiego.gov
Ongoing Construction and Related Updates:
- Genesee closed at SR 52 for Pure Water Pipelines work from April 11 – 14; details at: https://www.universitycitynews.org/UCCA/PureWaterApr2025
- Paving work on Gullstrand north of Governor: details at: https://www.universitycitynews.org/UCCA/GullstrandRepaving
- Water and Sewer Main work on Governor, Stadium, Pennant, Stresemann and adjacent streets – construction continues for the “University City Improvement 1” Project: Details and street map posted at: https://www.universitycitynews.org/UCCA/March2025ConstructionUpdate
- Pure Water construction at the Genesee and Nobel intersection has been delayed. Details available at: https://www.universitycitynews.org/UCCA/PureWaterMar2025
- Ramp closures expected due to the Governor Drive bridge widening project at the I-805. Details at: https://www.universitycitynews.org/UCCA/GovernorBridge-at-I-805